CASE STUDIES

14 inch cargo line

About the project

Integrity issue

The weld on a 14 inch weld neck flange from a hydrocarbon cargo line on a FPSO off the west coast of Africa was suffering from preferential internal corrosion. It was proposed to use a Futurewrap composite repair to reinstate the strength and seal the potential threat of a through wall defect. 

Design 

The design of the Futurewrap repair was according to ISO 24817. The design approach was to strengthen and locally leak seal. The design parameters were; internal pressure 2 bar, temperature 400C, design lifetime 3 years. The repair design resulted in a thickness of 5 mm (6 layers) of Futurewrap Glass/LT composite repair with an axial length of 2000 mm.

Installation

The installation steps are shown in the photographs. The potential threat of a through wall defect was dealt with by installing a clamp over the weld. The clamp and flange were then profiled with filler, followed by application of the 6 layers of Futurewrap Glass/LT repair. Full QA/QC measurements were made to demonstrate that the Futurewrap repair was applied in accordance with ISO 24817. 

Summary

A 14 cargo line suffering internal corrosion at a weld neck flange was repaired using a Futurewrap Glass/LT composite repair.  The repair was completed within 5 days allowing the pipework to be returned to its original integrity.

case 14.1
Initial condition of pipework with sealing clamp
case 14.2
After profiling
case 14.3
Final cured repair

INTERESTED?

Let’s talk about your project